Bushfire planning: SPP 3.7
How SPP 3.7 Bushfire applies in WA: checking the bushfire prone map, BAL assessments, Bushfire Management Plans, BAL-40 limits and building permits.

Large parts of Western Australia are designated bushfire prone on the Map of Bush Fire Prone Areas. On designated land, a subdivision or development proposal may need a Bushfire Attack Level (BAL) assessment or a Bushfire Management Plan before it can be decided, and new houses may need to meet bushfire construction standards.
This guide from Trace Planning, the town planning division of Trace Enterprises, explains how State Planning Policy 3.7 Bushfire works and what to prepare. Our statutory planning team prepares development and subdivision applications on bushfire prone land.



State Planning Policy 3.7 Bushfire (SPP 3.7) is the Western Australian Planning Commission (WAPC) policy for planning in bushfire prone areas. It was prepared under section 26 of the Planning and Development Act 2005 (WA), replaced the 2015 policy and became operational on 18 November 2024. It is read with the Planning for Bushfire Guidelines (November 2024). In the words of SPP 3.7, "The preservation of life and the management of bushfire impact are paramount."
Check whether your land is bushfire prone
Bushfire prone areas are designated by the Fire and Emergency Services Commissioner under section 18P of the Fire and Emergency Services Act 1998 (WA). The Office of Bushfire Risk Management, part of the Department of Fire and Emergency Services (DFES), maintains the Map of Bush Fire Prone Areas. The current version came into effect on 13 December 2025. To check a lot, search the address on the online map at maps.slip.wa.gov.au/landgate/bushfireprone.
DFES explains that a bushfire prone area includes bushfire prone vegetation plus a 100 metre buffer, so it can cover cleared land. The map flags that planning and building requirements may apply, depending on what you propose.
If you think the map is wrong for your lot, contact your local government.
Area 1 (Urban) and Area 2
SPP 3.7 describes Area 1 (Urban) as built-up urban areas where the risk posed by bushfire is lower. Area 2 is the rest of the designated land. The split matters most for strategic proposals, such as scheme amendments. Subdivision and development triggers turn on the BAL.
What a Bushfire Attack Level is
A Bushfire Attack Level (BAL) measures how exposed a building is to ember attack, radiant heat and direct flame contact. The six ratings come from Australian Standard AS 3959 Construction of buildings in bushfire-prone areas, referenced in the Building Code of Australia.
| Rating | What it indicates |
|---|---|
| BAL-LOW | Not enough risk to warrant specific construction requirements |
| BAL-12.5 | Ember attack, radiant heat up to 12.5 kW/m² |
| BAL-19 | Increasing ember attack and debris, up to 19 kW/m² |
| BAL-29 | Increasing ember attack and debris, up to 29 kW/m² |
| BAL-40 | Increased likelihood of flame contact, up to 40 kW/m² |
| BAL-FZ (Flame Zone) | Direct exposure to the fire front, above 40 kW/m² |
The higher the rating, the higher the construction standard. SPP 3.7 presumes against new habitable buildings above BAL-29.
BAL assessment or BAL Contour Map
A BAL Contour Map is a scale map of a lot showing indicative BAL ratings from the classified vegetation around it. It is typically used at subdivision stage, and where several habitable buildings are proposed. A BAL assessment is used at development application and building permit stage, once the building location is known. A basic BAL assessment can be used where no classified vegetation is within 100 metres, or 50 metres for grassland.
When SPP 3.7 applies to your proposal
In a designated area, the policy applies where a proposal intensifies development or land use, adds residents, visitors or employees, or adversely affects bushfire risk. The trigger then depends on the proposal.
| Proposal | Policy applies where |
|---|---|
| Structure plan or subdivision | BAL above BAL-LOW |
| Single house or ancillary dwelling, lot over 1,100 m², not on reticulated water | BAL above BAL-LOW |
| Single house or ancillary dwelling, lot over 1,100 m², on reticulated water | BAL-40 or BAL-FZ |
| Other habitable buildings | BAL-40 or BAL-FZ |
| Vulnerable land use, caravan park, nature-based park or camping ground | BAL above BAL-LOW |
| Single house or ancillary dwelling, lot of 1,100 m² or less | Policy does not apply |
In short, the planning policy reaches further on larger lots without scheme water, in subdivisions and for vulnerable uses. Building controls apply separately.
The Guidelines exempt subdivisions that do not increase development potential, sheds, garages and pools at least six metres from a habitable building, and minor works or changes of use that do not add occupants or increase bushfire risk.
The deemed provisions
Bushfire approval triggers also sit in Part 10A of Schedule 2 of the Planning and Development (Local Planning Schemes) Regulations 2015 (WA). These deemed provisions apply to all local planning schemes and prevail over inconsistent scheme provisions on bushfire. The Guidelines explain that they keep development approval in place for certain bushfire prone development that would otherwise be exempt, such as development that complies with the Residential Design Codes.
When a Bushfire Management Plan is needed
Where the policy applies, strategic proposals, subdivision applications and development applications must be accompanied by a Bushfire Management Plan (BMP). SPP 3.7 describes a BMP as setting out short, medium and long-term risk management strategies for the life of the development. It includes:
- a Bushfire Hazard Level assessment, BAL Contour Map or BAL assessment
- environmental and biodiversity values, including vegetation affected by clearing
- where required, an assessment of the surrounding area out to about 2 kilometres
- an assessment against the protection criteria in the Guidelines.
For a single house, a BMP should accompany the application where the pre-development BAL assessment exceeds 29 kW/m².
The protection criteria cover four elements: location, siting and design, vehicular access, and water supply. Each is met through acceptable solutions, an outcomes-based approach, or both. The outcomes-based approach is for complex sites, and the explanatory notes say a Level 3 practitioner should prepare it. A common acceptable solution is an asset protection zone, a managed area around the building wide enough to keep radiant heat at or below 29 kW/m².
BAL-40 and Flame Zone sites
SPP 3.7 sets a presumption against approving development sites or habitable buildings where radiant heat exceeds 29 kW/m², which means BAL-40 or BAL-FZ. For non-vulnerable habitable buildings, an exception can be considered where all of these apply:
- the lot was created before December 2015
- site characteristics or environmental values prevent BAL-29 being achieved
- reducing the footprint or redesigning is not practical or appropriate.
Vulnerable land uses
SPP 3.7 defines a vulnerable land use as one likely to present evacuation challenges, because it is designed for people who are less physically or mentally able, because of its building design, use or number of people, or because it involves visitors unfamiliar with the area. Section 8 of the Guidelines covers vulnerable tourism, commercial and industrial uses, vulnerable Class 9 buildings, caravan parks, nature-based parks and camping grounds.
A development application for a vulnerable land use needs a Bushfire Emergency Plan as well as a BMP. At subdivision stage, the BMP should consider evacuation and shelter options instead.
The 2015 policy also had a high-risk land use category, for uses that may lead to the ignition, prolonged duration or increased intensity of a bushfire. The explanatory notes say the 2024 policy removed it, as those activities are regulated under other legislation, and decision-makers can still consider bushfire risk under clause 67 of the deemed provisions.
How planning ties to the building permit
Development approval and a building permit are separate. The Building Regulations 2012 (WA) adopt the Building Code of Australia, whose bushfire requirements in designated areas cover Class 1, 2 and 3 buildings, associated Class 10a buildings such as garages and decks, and Class 9 vulnerable use buildings such as schools and residential care.
For houses, AS 3959 is a deemed-to-satisfy route. The building surveyor relies on the bushfire assessment, typically undertaken by a BAL assessor, to set the construction requirements. Accreditation bodies recognised by the State Government accredit Level 1 BAL assessors and Level 2 and Level 3 bushfire planning practitioners.
Building standards are generally not retrospective. A new house on a 700 m² designated lot may need no bushfire planning approval, but still has to meet the BAL construction requirements.
Practical steps
- Check the map for your lot, and whether it is in Area 1 (Urban) or Area 2.
- Work out the trigger from the lot size, water connection and proposed use.
- Commission a BAL assessment or BAL Contour Map before the design is fixed, so buildings can be sited to reach BAL-29 or lower.
- Speak with the local government early in the process, as DFES recommends.
- Carry the BAL through to the building permit.
How Trace Planning helps
Trace Planning prepares development applications, subdivision applications and planning reports through our statutory planning service. On bushfire prone land, a bushfire consultant prepares the BAL assessment, BAL Contour Map or BMP, and we coordinate with them so the planning application and the bushfire work line up.
If you plan to divide land, see our subdivision service and read Can I subdivide my block in Perth? All our services are on the urban and regional planning page.
Talk to a town planner about your site.
Frequently asked questions
How do I check if my property is in a bushfire prone area in WA?
Search the address on the Map of Bush Fire Prone Areas at maps.slip.wa.gov.au/landgate/bushfireprone, linked from the DFES website. If the mapping looks wrong, contact your local government.
Do I need a BAL assessment to build a house in a bushfire prone area?
For the building permit, the construction requirements depend on the BAL, and the building surveyor relies on a bushfire assessment, typically undertaken by a BAL assessor, to set them. A planning BAL assessment is needed where SPP 3.7 applies, for example a house on a lot over 1,100 m² without reticulated water and above BAL-LOW.
Who prepares a Bushfire Management Plan?
The WAPC strongly recommends an accredited Level 2 or Level 3 bushfire planning practitioner, at the level suited to the complexity of the proposal. An outcomes-based approach should be prepared by a Level 3 practitioner.
This article is general information as at November 2026, not legal advice.
References
All accessed 20 November 2026.
- Western Australian Planning Commission, State Planning Policy 3.7 Bushfire, November 2024, operational 18 November 2024. planning.wa.gov.au
- Western Australian Planning Commission, Planning for Bushfire Guidelines, November 2024, operational 18 November 2024. planning.wa.gov.au
- Western Australian Planning Commission, State Planning Policy 3.7 Bushfire: Explanatory notes. planning.wa.gov.au
- Department of Planning, Lands and Heritage, State Planning Policy 3.7 Bushfire web page, last updated 22 September 2026. planning.wa.gov.au
- Government of Western Australia, Western Australia gets new bushfire policy and map, 4 October 2024. wa.gov.au
- Western Australian Planning Commission, State Planning Policy 3.7 Planning in Bushfire Prone Areas, December 2015 (repealed). wa.gov.au
- Planning and Development (Local Planning Schemes) Regulations 2015 (WA), as at 6 October 2026, Schedule 2 Part 10A. legislation.wa.gov.au
- Department of Fire and Emergency Services, Bushfire prone areas. dfes.wa.gov.au
- Department of Fire and Emergency Services, Map of Bush Fire Prone Areas: Frequently asked questions, 2023. dfes.wa.gov.au
- Building and Energy, Building in bushfire prone areas, last updated 31 August 2026. wa.gov.au
Photo credits (Wikimedia Commons): Houses among bushland, Gooseberry Hill: Gnangarra, CC BY 2.5 AU.
Other latest news
Talk to our team
Our archaeologists, ecologists and town planners can tell you what this means for your site.











































-p-500.jpg)