Subdivision in WA: step by step

How subdivision works in WA, stage by stage: feasibility, the WAPC application, referral, conditions and clearances, plan endorsement and new titles.

Subdivision of land | Trace Enterprises

Subdividing land in Western Australia follows a set order: check what the land allows, prepare a plan, apply to the Western Australian Planning Commission (WAPC), meet the conditions of approval, then have the surveyed plan endorsed and new titles issued by Landgate.

This guide sets out each stage as at October 2026, who is involved and what you hold at the end of it. To test whether your block qualifies before you start, use our Can I subdivide my block? checklist.

Most subdivisions in WA pass through the same stages. The Planning and Development Act 2005 (WA) says land is not to be subdivided without approval, and for freehold (green title) and survey-strata lots that approval comes from the WAPC. After approval, the conditions are cleared, a licensed surveyor's plan is endorsed, and Landgate creates the new titles. Built strata follows a separate path, covered under Stage 3.

The stages at a glance

The table summarises who does what at each stage of a freehold or survey-strata subdivision.

Subdivision in WA: stages, people and outcomes
StageWho is involvedWhat you get
1. Feasibility checkYou and your planner, using the local planning scheme and R-CodesA view on whether the lots can meet the R-Code and scheme
2. Feature survey and planSurveyor and plannerA plan of subdivision drawn over an up-to-date feature survey
3. ApplicationYou or your consultant, lodging Form 1A with the WAPCA lodged application
4. Referral and decisionLocal government, service providers, the WAPCApproval with or without conditions, or a refusal
5. Condition clearanceYou, the local government, Water Corporation and other clearing agenciesA clearance for each condition
6. Survey plan and endorsementLicensed surveyor, Landgate, the WAPC (Form 1C)A deposited or survey-strata plan endorsed by the WAPC
7. New titlesRegistered proprietors, LandgateA separate title for each new lot

In short, the WAPC decides the application and endorses the final plan, while the local government and service providers advise on conditions and confirm when each one has been met.

Stage 1: Check what the land allows

Start with the zoning and density code (R-Code) that applies to the lot. PlanWA, the Department of Planning, Lands and Heritage's public mapping tool, shows local planning schemes, region schemes and heritage information across the State.

For residential land, the WAPC's Operational Policy 2.2 says the minimum and average lot size and frontage requirements of the relevant R-Code form the basis for subdivision. Our guide R-Codes explained: R20 to R40 works through those figures.

Fees and charges are covered in our guide to subdivision costs in Perth.

Policy under review

The Department has proposed repealing Operational Policy 2.2 and moving its remaining provisions into a draft operational policy. Public comment is open from 24 October 2026 until 26 February 2027. The Department expects changes to begin taking effect later in 2027, subject to consultation, endorsement and approval. Until then, Operational Policy 2.2 remains the published policy.

Stage 2: Commission a feature survey and draw the plan

The WAPC's application guide says every subdivision plan must be based on an accurate and up-to-date feature survey. That survey records existing features such as buildings and driveways, and the proposed lots are drawn over it.

Where relevant, the guide asks for supporting information to go with the plan, including:

  • earthworks of more than 300 mm;
  • drainage and stormwater changes;
  • availability of water, sewer, electricity and gas;
  • heritage significance and environmental features, including native vegetation;
  • bushfire risk documentation in a designated bushfire prone area;
  • nearby and previous land uses that may affect the proposal, such as contaminated sites.

You must also check that no restrictive covenants apply to the land. Our guide Green title vs strata in WA helps you settle the title type.

Stage 3: Lodge the application

Freehold and survey-strata subdivisions are applied for on Form 1A. The same form covers leasehold (survey-strata) and community titles (land) schemes, but a separate application is needed for each application type.

The WAPC's guide says applications should be lodged online through Planning Online, and the fee is payable at lodgement. The applicant signs the form, and all landowners, or their agents with written authority, must sign it too.

Built strata takes a different path

A built strata plan is approved under section 15 of the Strata Titles Act 1985 (WA), using Form 15A rather than Form 1A. The WAPC has delegated its power to decide built strata applications, other than leasehold, to local governments, so built strata applications are lodged with, and usually decided by, the local government, although the WAPC can call in an application in an area of State or regional significance. Vacant strata lots and leasehold schemes still go to the WAPC.

A built strata approval lasts two years from the decision. Once conditions are met, a Form 15C is lodged for endorsement.

Stage 4: Referral and decision

The WAPC refers each application to the local government, service providers and any other public authority the proposal may affect. The Department's flow chart of the subdivision process shows these bodies have 42 days to respond with any objections or recommendations.

Water Corporation, for example, assesses the water, wastewater and drainage services the new lots will need and advises the WAPC.

The WAPC then approves the application, with or without conditions, or refuses it. The flow chart sets a statutory period of 90 days for the decision, unless you and the WAPC agree in writing to a longer period. If no decision is made in that time, you can give written notice and the application is treated as refused. These are statutory periods, and actual timing varies.

If the WAPC refuses the application or imposes conditions you do not accept, you can ask it to reconsider on Form 3A within 28 days of the decision (section 144 of the Act for a refusal, section 151 for conditions). You can also apply to the State Administrative Tribunal for a review within 28 days (section 251).

Stage 5: Meet and clear the conditions

Conditions of approval are drafted from the Model Subdivision Conditions Schedule (December 2025), which groups them into 14 parts, among them water and sewer, drainage and site works, transport, roads and access, fire and emergency, heritage, and environment.

For residential lots, Operational Policy 2.2 makes reticulated sewerage mandatory for new subdivisions, subject to limited exceptions. The WAPC will also normally require underground power, having regard to the licensed service provider's advice.

A clearance is advice from the authority named in a condition that the requirement has been met. The schedule says the applicant is responsible for obtaining all clearances, the WAPC is the clearing agency where none is named, and the WAPC arbitrates if an agency and an applicant disagree.

Each agency runs its own process. Water Corporation sets its requirements, which may include servicing works and charges, in an agreement with a clearance checklist, and issues the clearance after the checklist is complete and the invoice is paid. The Department's flow chart notes that, under section 157 of the Act, the subdivision approval also gives you approval under the planning scheme for works needed to enable the subdivision or to meet its conditions.

Stage 6: Survey plan and WAPC endorsement

A licensed surveyor prepares the deposited plan or survey-strata plan and lodges it with Landgate. The surveyor can lodge it before all civil works are complete, so Landgate can examine it while works continue.

Once Landgate has certified the plan correct, it sends the plan to the WAPC on receipt of the surveyor's release letter. You apply for endorsement on Form 1C. The WAPC endorses the plan when it is satisfied that the plan matches the approval and every condition has been met.

Timing matters here. Under section 145A of the Act, approval is valid for three years for five lots or fewer, and four years for six lots or more. The conditions must be met and the plan submitted for endorsement within that period.

You can apply on Form 4A, under section 145A of the Act, for one extension of two years to the time for submitting the plan. You must show you have done everything reasonably practicable, such as having works substantially progressed, and the WAPC must be satisfied that the planning requirements for the area have not changed significantly since approval.

Stage 7: New titles from Landgate

After endorsement, the owners apply to Landgate for new titles on an Application for new titles (subject to survey). Landgate's guide says all registered proprietors sign it, and any documents needed to approve the plan are lodged with it. Where the land is mortgaged, the first mortgagee must consent in writing, and restrictive covenants that the subdivision would breach must be modified or discharged beforehand.

The application must be made within two years of the WAPC endorsement date. Landgate notes that, under section 146 of the Act, the Registrar of Titles is not to create titles outside that period. A deposited plan that is not dealt with in time is marked expired, and a new WAPC approval is then needed. Once the titles are registered, the plan's status changes to approved.

Statutory periods and time limits

The fixed periods in the process are set out below.

Statutory periods and time limits
PeriodWhat it applies to
42 daysLocal government and other referral agencies respond to the WAPC
90 daysThe WAPC decides the application, unless a longer period is agreed in writing
28 daysYou ask the WAPC to reconsider (Form 3A) or apply to the State Administrative Tribunal
Three years (five lots or fewer) or four years (six lots or more)You meet the conditions and submit the plan to the WAPC for endorsement
Two years from the decisionA built strata approval (Form 15A) remains valid
Two years from endorsementYou apply to Landgate for new titles

The referral and decision periods are statutory periods, not promises, while the approval and title periods are deadlines: missing them means seeking a new approval.

How Trace Planning helps

Trace Planning, the town planning division of Trace Enterprises, prepares subdivision applications for landowners in Perth and regional WA. We can check the zoning and R-Code, work with your surveyor on the plan, prepare and lodge the Form 1A application, respond to referral comments, and work through condition clearances with the local government and service providers. Where heritage or environmental matters arise, Trace Archaeology and Trace Ecology can assess them alongside the planning work. See our town planning services in Perth, or talk to a town planner about your site.

Frequently asked questions

How long does subdivision take in WA?

There is no single overall timeframe. Referral agencies have a statutory period of 42 days to respond, and the WAPC has 90 days to decide unless a longer period is agreed. After that, timing depends on how long the conditions take to meet, within the three or four year life of the approval.

Do I apply to the council or the WAPC?

Freehold and survey-strata subdivisions are lodged with the WAPC on Form 1A, and the WAPC refers them to the local government for comment. Built strata applications on Form 15A are lodged with the local government, which decides them under delegation from the WAPC.

How long is a subdivision approval valid?

A Form 1A approval is valid for three years for five lots or fewer, and four years for six lots or more. The WAPC can grant one extension of two years on a Form 4A application. A built strata approval lasts two years from the decision, and the Form 15A guide says it will not be extended.

This article is general information as at October 2026, not legal advice.

References

All accessed 30 October 2026.

  1. Planning and Development Act 2005 (WA), version 04-af0-00, current from 19 February 2026, Part 10 (sections 135, 144, 145A, 146, 151 and 157) and section 251. legislation.wa.gov.au: Planning and Development Act 2005
  2. Western Australian Planning Commission, Application Guide: Subdivision Applications and Fees, Version 10.7, July 2026. planning.wa.gov.au: subdivision application guide
  3. Department of Planning, Lands and Heritage, Subdivision application forms, guidelines and checklists (last updated 14 July 2026). planning.wa.gov.au: subdivision forms
  4. Department of Planning, Lands and Heritage, Flow chart of subdivision process (undated). planning.wa.gov.au: subdivision process flow chart
  5. Western Australian Planning Commission, Form 4A: Application for extending the period of time for submission of a diagram or plan of survey, section 145A(3), Version 1.2, July 2026. planning.wa.gov.au: Form 4A
  6. Western Australian Planning Commission, Form 15A Application Guide (built and vacant strata), Version 1.3, December 2024. planning.wa.gov.au: Form 15A guide
  7. Western Australian Planning Commission, Operational Policy 2.2: Residential Subdivision, 31 May 2024 (clauses 4.1.2, 4.2.1, 4.8.1 to 4.8.3). wa.gov.au: Operational Policy 2.2
  8. Department of Planning, Lands and Heritage, Operational policy 2.2: Residential subdivision (publication page, last updated 24 October 2026). wa.gov.au: Operational Policy 2.2 review
  9. Department of Planning, Lands and Heritage, Residential Design Codes Review (last updated 24 October 2026). wa.gov.au: R-Codes review
  10. Western Australian Planning Commission, Operational Policy 1.1: Subdivision of land, general principles, February 2020 (clauses 4.2.1 and 4.3.1). wa.gov.au: Operational Policy 1.1
  11. Western Australian Planning Commission, Model Subdivision Conditions Schedule, December 2025. wa.gov.au: Model Subdivision Conditions Schedule
  12. Water Corporation, How to subdivide. watercorporation.com.au: how to subdivide
  13. Landgate, SPP-20 Plan Approval Requirements, Version 2, 10 August 2021. landgate.wa.gov.au: SPP-20
  14. Landgate, SUB-01 Subdivision. landgate.wa.gov.au: SUB-01
  15. Landgate, SUB-02 Application for New Titles, Version 10, 29 October 2024. landgate.wa.gov.au: SUB-02
  16. Department of Planning, Lands and Heritage, PlanWA (last updated 27 March 2025). planning.wa.gov.au: PlanWA