Section 18 notices & heritage approvalsWestern Australia
Getting development approved where Aboriginal heritage is present takes more than a survey. It takes a section 18 agent who knows the Aboriginal Heritage Act 1972, prepares a notice the decision-maker can assess on its evidence, and has working relationships with Aboriginal Corporations and Native Title holders.
- Before lodgementNo statutory clockHeritage survey, risk assessment and the notice itself
- 70 daysCommitteeRecommendation to the Minister, from receipt of the notice
- 28 daysMinisterDecision on consent, or as soon as practicable after that
- 28 daysReviewGeneral period to apply to the State Administrative Tribunal
- Legislation
- Aboriginal Heritage Act 1972 (WA), section 18
- Lodged with
- Department of Planning, Lands and Heritage, through the ACHknowledge portal
- Considered by
- Aboriginal Cultural Heritage Committee
- Decided by
- Minister for Aboriginal Affairs
A section 18 agent for the whole application
Trace acts as section 18 agent across Western Australia. Section 18 consent allows activities to proceed where Aboriginal cultural heritage sites are present, and we manage every step of seeking it.
We act for
- Developers
- Miners
- Exploration companies
- Infrastructure builders
- Government agencies
- 1
Heritage survey & risk assessment
The heritage survey and risk assessment that give the notice its supporting heritage information.
- 2
Preparation & lodgement
We prepare the notice and lodge it with the Department of Planning, Lands and Heritage through the ACHknowledge portal.
- 3
Engagement with Native Title Parties
We engage with the Native Title Parties for the land the notice covers.
- 4
Management through to decision
We liaise with the Department and native title parties until the Minister's decision is made.
How long a section 18 decision takes
The Aboriginal Heritage Act 1972 sets a period for the Committee, a period for the Minister and a period for seeking review. The bar below draws those periods to scale.
- 1The notice is received and the Committee's 70 days begin.
- 2The Committee sends its recommendation to the Minister.
- 3The Minister's decision is published.
- Before lodgementNo statutory clock
The heritage survey and risk assessment are completed, Native Title Parties are engaged and the notice is prepared with its supporting heritage information. The notice is then lodged online with the Department of Planning, Lands and Heritage.
- Committee: 70 daysFrom receipt of the notice
The Aboriginal Cultural Heritage Committee considers the notice. It has 70 days from receiving the notice to send its recommendation to the Minister.
- Extension: up to 30 daysOnce only
The 70 days can be extended once, by up to 30 days. Time spent waiting for information the Committee has asked for doesn't count.
- Minister: 28 daysAfter the recommendation
The Minister for Aboriginal Affairs then has 28 days to decide, or as soon as practicable after that.
- Review: generally 28 daysAfter the decision is published
The landowner or a native title party can apply to the State Administrative Tribunal for review of the Minister's decision, generally within 28 days of the decision being published.
This is a summary of the statutory periods, not legal advice. For the detail, read our guide to section 18 consent or the step-by-step guide to heritage approvals in WA.
Aboriginal heritage auditing & compliance
Not every project needs a section 18 notice. A heritage audit shows where a project stands and what it needs to proceed lawfully and respectfully.
- Site audits
Site audits that assess heritage risk across your project areas.
- Review of existing management plans
A review of your existing cultural heritage management plans for compliance.
- Advice you can act on
Clear, actionable advice on what the project needs to proceed lawfully and respectfully.
- Cultural heritage management plans
New plans prepared to satisfy regulatory requirements and the expectations of Aboriginal communities.
Engagement with Aboriginal Corporations & Native Title Holders
Free, prior and informed consent from the appropriate Native Title Holders is the foundation of a project that proceeds without dispute.
We facilitate engagement between developers, miners and Aboriginal Corporations, drawing on working relationships with Aboriginal Corporations and Native Title holders.
Aboriginal archaeology and anthropology →Heritage monitoring & compliance projects
All Trace projects →Broome Pioneer Cemetery monitoring
- For
- Shire of Broome
- Date
- June 2022
CBH heritage surveys & monitoring
- For
- CBH Group
- Region
- Wheatbelt
Unexpected finds procedure
- Type
- Unexpected finds procedure
- Region
- Northern Territory
Guides to section 18 & heritage approvals in WA
All guides →Section 18 questions we are asked most
Short answers on section 18 notices, timeframes and review. If yours is not here, call us on (08) 9446 6185.
What is a section 18 notice?
How long does a section 18 decision take?
Can a section 18 decision be reviewed?
Can Trace lodge a section 18 notice for us?
Every Section 18 application starts with the right consultant
Whether you need Section 18 consent, heritage auditing or a Cultural Heritage Management Plan, Trace Archaeology is ready to help.