Getting development approved where Aboriginal heritage is present takes more than a survey. It takes a section 18 agent who knows the Aboriginal Heritage Act 1972, prepares a notice the decision-maker can assess on its evidence, and has working relationships with Aboriginal Corporations and Native Title holders.

Section 18 pathwayAt a glance
  1. Before lodgementNo statutory clockHeritage survey, risk assessment and the notice itself
  2. 70 daysCommitteeRecommendation to the Minister, from receipt of the notice
  3. 28 daysMinisterDecision on consent, or as soon as practicable after that
  4. 28 daysReviewGeneral period to apply to the State Administrative Tribunal
Periods set by the Aboriginal Heritage Act 1972. One extension and pauses can apply.Full timeline
Legislation
Aboriginal Heritage Act 1972 (WA), section 18
Lodged with
Department of Planning, Lands and Heritage, through the ACHknowledge portal
Considered by
Aboriginal Cultural Heritage Committee
Decided by
Minister for Aboriginal Affairs
01Section 18 agent

A section 18 agent for the whole application

Trace acts as section 18 agent across Western Australia. Section 18 consent allows activities to proceed where Aboriginal cultural heritage sites are present, and we manage every step of seeking it.

We act for

  • Developers
  • Miners
  • Exploration companies
  • Infrastructure builders
  • Government agencies
  1. Heritage survey & risk assessment

    The heritage survey and risk assessment that give the notice its supporting heritage information.

  2. Preparation & lodgement

    We prepare the notice and lodge it with the Department of Planning, Lands and Heritage through the ACHknowledge portal.

  3. Engagement with Native Title Parties

    We engage with the Native Title Parties for the land the notice covers.

  4. Management through to decision

    We liaise with the Department and native title parties until the Minister's decision is made.

02Section 18 timeline / Statutory periods

How long a section 18 decision takes

The Aboriginal Heritage Act 1972 sets a period for the Committee, a period for the Minister and a period for seeking review. The bar below draws those periods to scale.

Section 18 statutory periods, drawn to scaleBar length = number of days
  1. The notice is received and the Committee's 70 days begin.
  2. The Committee sends its recommendation to the Minister.
  3. The Minister's decision is published.
  1. Before lodgementNo statutory clock

    The heritage survey and risk assessment are completed, Native Title Parties are engaged and the notice is prepared with its supporting heritage information. The notice is then lodged online with the Department of Planning, Lands and Heritage.

  2. Committee: 70 daysFrom receipt of the notice

    The Aboriginal Cultural Heritage Committee considers the notice. It has 70 days from receiving the notice to send its recommendation to the Minister.

  3. Extension: up to 30 daysOnce only

    The 70 days can be extended once, by up to 30 days. Time spent waiting for information the Committee has asked for doesn't count.

  4. Minister: 28 daysAfter the recommendation

    The Minister for Aboriginal Affairs then has 28 days to decide, or as soon as practicable after that.

  5. Review: generally 28 daysAfter the decision is published

    The landowner or a native title party can apply to the State Administrative Tribunal for review of the Minister's decision, generally within 28 days of the decision being published.

This is a summary of the statutory periods, not legal advice. For the detail, read our guide to section 18 consent or the step-by-step guide to heritage approvals in WA.

03Auditing & compliance / Audit sheet

Aboriginal heritage auditing & compliance

Not every project needs a section 18 notice. A heritage audit shows where a project stands and what it needs to proceed lawfully and respectfully.

Heritage audit and complianceScope
  • Site audits

    Site audits that assess heritage risk across your project areas.

  • Review of existing management plans

    A review of your existing cultural heritage management plans for compliance.

  • Advice you can act on

    Clear, actionable advice on what the project needs to proceed lawfully and respectfully.

  • Cultural heritage management plans

    New plans prepared to satisfy regulatory requirements and the expectations of Aboriginal communities.

04Engagement

Engagement with Aboriginal Corporations & Native Title Holders

Free, prior and informed consent from the appropriate Native Title Holders is the foundation of a project that proceeds without dispute.

ProponentDevelopers and miners
Trace ArchaeologyFacilitates the engagement
CommunityAboriginal Corporations and Native Title Holders

We facilitate engagement between developers, miners and Aboriginal Corporations, drawing on working relationships with Aboriginal Corporations and Native Title holders.

Aboriginal archaeology and anthropology
07Questions

Section 18 questions we are asked most

Short answers on section 18 notices, timeframes and review. If yours is not here, call us on (08) 9446 6185.

What is a section 18 notice?
Under section 18 of the Aboriginal Heritage Act 1972 (WA), a landowner who wants to use land in a way that is likely to affect an Aboriginal site can give notice seeking the consent of the Minister for Aboriginal Affairs. The notice is lodged online with the Department of Planning, Lands and Heritage and considered by the Aboriginal Cultural Heritage Committee, which makes a recommendation to the Minister.
How long does a section 18 decision take?
The Committee has 70 days from receiving the notice to send its recommendation to the Minister. That can be extended once by up to 30 days, and time spent waiting for information the Committee has asked for doesn't count. The Minister then has 28 days to decide, or as soon as practicable after that.
Can a section 18 decision be reviewed?
Yes. The landowner or a native title party can apply to the State Administrative Tribunal for review of the Minister's decision, generally within 28 days of the decision being published.
Can Trace lodge a section 18 notice for us?
Yes. We act as agents for Section 18 notices: we prepare the supporting heritage information, lodge the notice and liaise with the Department and native title parties through to the decision.

Every Section 18 application starts with the right consultant

Whether you need Section 18 consent, heritage auditing or a Cultural Heritage Management Plan, Trace Archaeology is ready to help.